High School Project Update for 4/4/16

WINCHESTER HIGH SCHOOL – SCHEDULED WORK UPDATE

Week of 04/03/2016

Building C:

o Install tile wainscoting in corridors level 2 & 3

o Install resilient tile flooring on level 3

o Install casework on level 2 & 3

o Install countertops on level 2 & 3

o Install fixtures on level 1

o Install terracotta veneer on north side •

Building E:

o MEP connections at D/E Connector

o Install/Insulate overhead MEP’s on level 2 and level 3

o Interior framing on level 2 & 3

o Painting on level 1

o Install arriscraft veneer on south & east sides o Install brick radius at south side

o Install curtain walls on south and north sides

• Sitework:

o Form, rebar, and place building E retaining wall

o Grading in C/E Courtyard

• April Vacation Forecast:

o Bldg A exterior Sachem sign removal and relocation over April Vacation

o Tree removal near teacher’s parking lot

o Fence reconfiguration at north-west corner of site

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s